The length of time required to recover the cost of an investment. Calculated as

Pay back period =

Using the following example:

Project \[C_0\] \[C_1\] \[C_2\] \[C_3\] Payback NPV at 10%
A
500 500 5000 3
2624
B
500 1800 0 2
C
1800 500 0 2
50
  1. The payback rule ignores all cash flows after the cut off date.
  2. The payback rule gives equal weight to all cash flows before the cutoff date.