Difference between revisions of "Pay back period"

From knowledgebase
Jump to navigation Jump to search
 
Line 1: Line 1:
−
Pay back period
+
The length of time required to recover the cost of an investment. Calculated as
 +
 
 +
'''Pay back period''' = <math>\frac{Cost of Project}{Annual Cash Inflows}</math>
 +
 
 +
Using the following example:
 +
{| class="wikitable"
 +
!Project
 +
!\[C_0\]
 +
!\[C_1\]
 +
!\[C_2\]
 +
!\[C_3\]
 +
!Payback
 +
!NPV at 10%
 +
|-
 +
|A
 +
|-2000
 +
|500
 +
|500
 +
|5000
 +
|3
 +
|+2624
 +
|-
 +
|B
 +
|-2000
 +
|500
 +
|1800
 +
|0
 +
|2
 +
|-58
 +
|-
 +
|C
 +
|-2000
 +
|1800
 +
|500
 +
|0
 +
|2
 +
|+50
 +
|-
 +
|}
 +
# The payback rule ignores all cash flows after the cut off date.
 +
# The payback rule gives equal weight to all cash flows before the cutoff date.
 
[[Category:finance]]
 
[[Category:finance]]
  

Latest revision as of 19:25, 27 August 2020

The length of time required to recover the cost of an investment. Calculated as

Pay back period =

Using the following example:

Project \[C_0\] \[C_1\] \[C_2\] \[C_3\] Payback NPV at 10%
A
500 500 5000 3
2624
B
500 1800 0 2
C
1800 500 0 2
50
  1. The payback rule ignores all cash flows after the cut off date.
  2. The payback rule gives equal weight to all cash flows before the cutoff date.